1-
Important and fixing thermal blamer
it's thick is 5 cm density 32-35.
2-
Importing and fixing a layer of
nylon.
3-
Importing and doing strings to form
the trends with rate 1%.
4-
Importing and doing foam concrete
with middle thickness 10 cm.
5-
Importing and doing a layer of
surveyor 2 cm.
6-
Importing and painting a layer of
primer foundation.
7-
Importing and fixing blamer of humid
Kuwait, Saudi or Emirate blamer 4 mm
200 gm polyester.
8-
Importing and doing surveyor for
protection 2 cm.
9-
Importing and fixing cement 40 x 40. |